I want to start my project by dividing up the various things the system needs to do, then put them into the order I plan to approach them. I want to start with requirements that are the most risky and most important to success first, and work my way down the list until I finish with items that are neither risky nor important.
This approach gives me several advantages. It’s not an issue in this case since I don’t have any deadlines to meet, but if this were a professional project and a deadline had to be pushed up, I am more likely to have a product that does the most essential things. If I had a fixed deadline and the project starts running long, I’m more likely to have a working product that’s just missing a few less important features. In an ideal world those don’t happen, but at the end of the project the parts that were risky and/or essential have had the most time to be tested and fine-tuned as the application matures.